Work is gathering pace at The Mikes  

Our loyal band of volunteers have been busy completing many tasks ahead of the pitch being dug up. 
 
Jobs completed so far include: 
 
Removal of the six foot concrete fence behind the Bowling Green End goal for reuse elsewhere 
Removal of the wooden fence adjacent to the Bowling Green for re use elsewhere 
Removal of 22 trees at the Bowling Green End and replacing the same number in a contained planting exercise, as requested by Birmingham City Council 
Removal of all eight floodlight pylons ready for new concrete bases to accommodate the new pitch levels 
Digging and installing the new bases on the main stand side of the ground 
Removal of the grass on the picnic area near to the tunnel, ready for the area to be resurfaced. 
Removal of concrete terracing ready for the extension to the main stand. 
Installation of the steel framework for the main stand extension 
Removal of the old stand fascia ready for new signage. 
Adjustment to the terracing to create more space in front of the supporters' toilets. 
There have been many volunteers helping their club, especially parents from our junior section, but special thanks go to Mark Imms, whose knowledge, skills and commitment have been invaluable to the club and have allowed so many essential tasks to be completed so quickly. 
Our Under 10s may never be seen again! 
For more fixtures, visit the gallery BY CLICKING HERE 
Our site uses cookies. For more information, see our cookie policy. Accept cookies and close
Reject cookies Manage settings